Hung Shui Kiu station
Proposed station site | |||||||||||
| General information | |||||||||||
| Location | Hung Shui Kiu Yuen Long District, Hong Kong | ||||||||||
| Coordinates | 22°25′55″N 113°59′18″E / 22.4319°N 113.9884°E | ||||||||||
| System | Under construction MTR rapid transit station (Project gazetted, construction began 2024) | ||||||||||
| Owned by | KCR Corporation | ||||||||||
| Operated by | MTR Corporation | ||||||||||
| Line | Tuen Ma line | ||||||||||
| Platforms | 2 side platforms | ||||||||||
| Tracks | 2 | ||||||||||
| Construction | |||||||||||
| Structure type | Elevated | ||||||||||
| Other information | |||||||||||
| Status | Approved, construction began 2024 | ||||||||||
| Station code | HSK | ||||||||||
| History | |||||||||||
| Opening | 2030 | ||||||||||
| Key dates | |||||||||||
| 2021 | Planning and design commences | ||||||||||
| 2023 | Project gazetted under the Railway Ordinance | ||||||||||
| 2024 | Expected commencement of construction | ||||||||||
| 2030 | Expected completion of construction | ||||||||||
| Services | |||||||||||
| |||||||||||
| |||||||||||
Hung Shui Kiu (Chinese: 洪水橋) is an under construction MTR station on the Tuen Ma line. It will be located at Hung Shui Kiu, Yuen Long.
It is expected to cost HK$4.1 billion in December 2018 prices.
The station may also be served by the proposed Hong Kong-Shenzhen Airport Rail Link between Hong Kong International Airport, Shenzhen Bao'an International Airport, Guangzhou Baiyun International Airport and Foshan Shadi Airport.
In March 2024, the Executive Council of Hong Kong approved the construction of the station. The station is expected to be finished by 2030.