Upper Kotmale Dam

Upper Kotmale Dam
The dam in March 2018.
Upper Kotmale Dam
Location of Upper Kotmale Dam in Sri Lanka
Official nameUpper Kotmale Dam
CountrySri Lanka
LocationTalawakele, Nuwara Eliya
Coordinates06°56′48″N 80°39′29″E / 6.94667°N 80.65806°E / 6.94667; 80.65806
PurposePower Generation
StatusOperational
Construction began2003
Opening date2012
Construction costRs. 44 billion
OwnerCeylon Electricity Board
Dam and spillways
Type of damGravity dam
ImpoundsKotmale River
Height (foundation)35 m (115 ft)
Length180 m (591 ft)
Width (crest)7 m (23 ft)
Spillways5
Spillway capacity3,300 m3/s (116,538.4 cu ft/s)
Reservoir
CreatesUpper Kotmale Reservoir
Total capacity800,000 m3 (28,000,000 ft3)
Surface area250,000 m2 (2,690,978 ft2)
Upper Kotmale Power Station
Coordinates07°02′32″N 07°12′00″E / 7.04222°N 7.20000°E / 7.04222; 7.20000
Commission date14 July 2012 (2012-07-14)
TypeRun-of-the-river
Turbines2 × 75 MW Francis-type
Installed capacity150 MW
Annual generation409 GWh
Website
https://ceb.lk/

The Upper Kotmale Dam (also known as the Upper Kotmale Hydropower Project, or UKHP) is located in Talawakele, within the Nuwara Eliya District, in the Central Province of Sri Lanka. The dam feeds the third largest hydroelectric power station in the country.