Grand Ethiopian Renaissance Dam

Grand Ethiopian Renaissance Dam
The main dam after full filling in August 2024
Interactive map of Grand Ethiopian Renaissance Dam
Official name
  • Amharic: ታላቁ የኢትዮጵያ ሕዳሴ ግድብ
  • Tigrinya: ግድብ ሕዳሰ ኢትዮጵያ
  • Oromo: Hidha Guddicha Haaromsa Itoophiyaa
CountryEthiopia
LocationGuba, Benishangul-Gumuz Region
Coordinates11°12′55″N 35°05′35″E / 11.21528°N 35.09306°E / 11.21528; 35.09306
PurposePower
StatusOperational
Construction began2 April 2011
Opening date21 July 2020 (21 July 2020)
Construction costUS$5 billion
OwnerEthiopian Electric Power
Dam and spillways
Type of damGravity, roller-compacted concrete
ImpoundsBlue Nile River
Height145 m (476 ft)
Length1,780 m (5,840 ft)
Elevation at crest655 m (2,149 ft)
Dam volume10,400,000 m3 (13,600,000 cu yd)
Spillways1 gated, 2 ungated
Spillway type6 sector gates for the gated spillway
Spillway capacity14,700 m3/s (520,000 cu ft/s) for the gated spillway
Reservoir
CreatesNigat Lake
Total capacity74×10^9 m3 (60,000,000 acre⋅ft)
Active capacity59.2×10^9 m3 (48,000,000 acre⋅ft)
Inactive capacity14.8×10^9 m3 (12,000,000 acre⋅ft)
Catchment area172,250 km2 (66,510 mi2)
Surface area1,874 km2 (724 mi2)
Maximum length246 km (153 mi)
Maximum water depth140 m (460 ft)
Normal elevation640 m (2,100 ft)
Power Station
OperatorEthiopian Electric Power
Commission date20 February 2022–August 2024
Turbines
Installed capacity5.15 GW
Capacity factor28.6%
Annual generation15.76 TWh (est., planned)
Website
www.hidasse.gov.et

The Grand Ethiopian Renaissance Dam (GERD or TaIHiGe; Amharic: ታላቁ የኢትዮጵያ ሕዳሴ ግድብ, romanizedTālāqu ye-Ītyōppyā Hidāsē Gidib, Tigrinya: ግድብ ሕዳሰ ኢትዮጵያ, Oromo: Hidha Guddicha Haaromsa Itoophiyaa), formerly known as the Millennium Dam and sometimes referred to as the Hidase Dam (Amharic: ሕዳሴ ግድብ, romanizedHidāsē Gidib, Oromo: Hidha Hidāsē), is a gravity dam on the Blue Nile River in Ethiopia. The dam is in the Metekel Zone of the Benishangul-Gumuz Region, close to the border with Sudan.

Constructed between 2011 and 2023, the dam's primary purpose is electricity production to relieve Ethiopia's acute energy shortage and to export electricity to neighbouring countries. With an installed capacity of 5.15 gigawatts, the dam is the largest hydroelectric power plant in Africa and among the 20 largest in the world.

The first phase of filling the reservoir began in July 2020 and in August 2020 the water level rose to an altitude of 540 meters (40 meters higher than the bottom of the river, which is at an altitude of 500 meters above sea level). The second phase of filling was completed on 19 July 2021, with water levels rising to an altitude of around 575 meters. The third filling was completed on 12 August 2022 to a level of an altitude of 600 metres (2,000 ft). The fourth filling was completed on 10 September 2023 with water levels at around 625 metres (2,051 ft). The fifth and last filling was completed in October 2024, with a final water level at altitude of around 640 metres (2,100 ft). According to Prime Minister Engineer Hailemariam Desalegns inauguration was set for the second half of 2025.

On 20 February 2022, the dam produced electricity for the first time, delivering 375 MW to the grid. A second 375 MW turbine was commissioned in August 2022. The third and fourth 400 MW turbines were commissioned in August 2024. The dam's official opening was 9 September 2025.